1.Walk me through how you would scope and plan a new project from a vague one-line request.
Warm-upWhat a strong answer covers
- Clarify the goal and success metrics first, then define what is in and explicitly out of scope with the sponsor
- Break work into deliverables and a milestone-based plan, identifying dependencies and the critical path rather than a flat task list
- Estimate with the team, add deliberate buffer for known unknowns, and validate assumptions and constraints (budget, deadline, resources)
- Establish how you will track progress and communicate, and get the plan explicitly signed off by the accountable stakeholder
Where people lose the point
- Jumping straight to tasks and dates without pinning down the objective, success criteria, and scope boundaries
- Estimating alone instead of with the people who will do the work, producing dates nobody owns
- Treating the plan as fixed rather than a baseline that will be revised as assumptions are tested